A New Era in Constituent Management
Project Timeline
Q3-4 FY25
Project Initiation
- Kindsight Ascend selected as new CRM tool
- Attain Partners selected as Implementation Partner
- Finalize contracts
- Project plan is formulated
- Meeting and communication cadence established
- Internal CRM Team formed
- ascend installation on Salesforce completed
- SalesForce training shared
2025
Q1 FY26
CRM Implementation Kick-off
- Self-guided Salesforce training
- Discovery starts for all elements of the project
- ascend configuration and build starts
- Bio-Demo focus for first 4 initial sprints
- Constituents, Organizations and related data
- Relationships, Affiliations and Employment
- Households
Q2 FY26
CRM Build: Bio-Demo + Data Migration
- Bio-Demo focus continues
- Data mapping and reporting
- Supporting Applications integrated
Q3 FY26
CRM Build: Gifts and Pledges + Data Migration
- Gifts and Pledges focus
- Appeals, Designations, and Credits
- Outright, Recurring, and Matching gifts
- Pledges, Planned Gifts and Payroll Deductions
- Batch Entry and Adjustments
2026
Q4 FY26
CRM Build: Gifts and Pledges + Data Migration
- Gifts and Pledges focus continues
- Data mapping and reporting
- Supporting Applications integrated
Q1 FY27
CRM Build: Membership/Giving Society, Prospect Research & Management + Data Migration
- Giving Societies and Society Memberships
- Membership Levels, Products and Benefits
- Membership management and payment processing
- Assignments, Briefings, Research requests and tracking, Wealth ratings, Strategies, Work plans, and Funding Interests
Q2 FY27
CRM Build: Prospect Research & Management, Stewardships and Endowments + Data Migration
- Prospect Research focus continues with Proposals, Contact Reports and Tasks
- Stewardship Activities and Tasks/Cases
- Endowment Financials, Stewardees, and Beneficiaries
- Naming Opportunities and Benefits
Q3 FY27
CRM Build: Backlog + End-to End Testing + Training
- Items identified during core Sprints that can be accomodated into the timeline/budget
- Implement Salesforce Maps
- Optional functionality as time permits
- Continue to validate data
- Batch Entry and Adjustments
2027
Q4 FY27
Deploy and Go Live
- Final Data Migration
- Post-Production Data Migration Support
- Outright, Recurring, and Matching gifts
- Pledges, Planned Gifts and Payroll Deductions
- Batch Entry and Adjustments